Project Delivery 360

Project execution & delivery — the active marquee-project book (765 kV lines, AIS/GIS substations, international EPC, RE-evacuation, the Ranjangaon expansion), completion, and where thin EPC margin is slipping against plan.

Bajel Projects Limited · FY26 (Mar'26, standalone audited anchor)
Bajaj Group's power-transmission & distribution EPC and tower/monopole manufacturing arm
1,400 employees · 1+ plants & units · 6 export markets
Executive read· the answer, then the moves

8 active projects are tracking below target margin, putting ₹53 Cr of thin EPC margin at stake — recoverable while the project is still in execution. With 3 of 9 projects needing attention and ₹1,610 Cr of contract value still to execute, the fastest margin recovery is on the projects already underway (commodity discipline + scope control).

2 of 2 headline metrics improving vs prior · still off target: Order Book ₹4,055 Cr vs ₹4,500 Cr, Book-to-Bill 1.2x vs 1.2x

Do now — ranked by urgency
  1. 1
    Recover margin on the Egypt 500 kV OHTL (EETC) project before it commissionsAct now
    Why it matters

    Egypt 500 kV OHTL (EETC) is 15% executed at 10% vs a 13% target — ₹12 Cr at stake that locks in once the project commissions.

    What's driving it
    • Egypt 500 kV OHTL (EETC): 10% vs 13% target (−3pt)
    • 8 projects below target, ₹53 Cr total at stake
    FYI
    • International EPC (MENA & Africa) · International (MENA · Africa)
    • Recover via scope discipline, commodity / escalation clauses & subcontract control before commissioning
  2. 2
    Execute the ₹1,610 Cr of remaining contract value against the ₹4,055 Cr order bookWatch
    Why it matters

    ₹1,610 Cr of contract value remains to execute across 9 active projects at 39% average completion — revenue books only as milestones commission.

    What's driving it
    • Active project value ₹2,620 Cr, ₹1,610 Cr still to execute
    • Order book ₹4,055 Cr, book-to-bill 1.16x
    FYI
    • 3 of 9 active projects need attention
    • Owner: Project Execution (Ajay Nagle) / PMO
📈 Clients, PGCIL & internationalisationStep 5 of 6 · deliver the order at marginExecution & Commissioning 360Order-to-Cash 360All journeys
🌐 Enterprise 360 modules· on Project / Job 360Browse all 31 views ▾
● LiveBuilt forProject Execution (Ajay Nagle)· project health & completionSegment heads / PMO· projects slipping on marginCFO· execution & project margin

Behind the ₹4,055 Cr order book sit live 765 kV lines, AIS/GIS substations, the Egypt 500 kV export and the Ranjangaon expansion. This view is where the order book becomes executed revenue — and where thin EPC margin erodes if a project runs long, scope creeps or steel/zinc spikes. 3 of 9 active projects need attention.

Data backing: project (active marquee projects) · kpi.arr (order book) · segment margins
₹4,055 Cr
Confirmed order book
committed, not yet executed
9
Active projects
in design / execution
₹2,620 Cr
Active project value
₹1,610 Cr still to execute
39%
Avg completion
weighted by count
8
Below-target margin
₹53 Cr at stake
The project book

Active marquee projects

Margin shown as actual / target — red where the project is tracking below plan.

ProjectClient / sponsorSegmentLocationContract valueCompleteMarginHealth
Kurnool-IV → Kurnool-III 765 kV D/C linePower Grid Corp (PGCIL)Power Transmission (Lines & Substations ≤765 kV)South (Karnataka · AP · Telangana · TN)₹420 Cr
45%
11% / 13%On track
Vindhyachal Pool–Prayagraj 765 kV D/C (87.3 km)Power Grid Corp (PGCIL)Power Transmission (Lines & Substations ≤765 kV)North (Delhi-NCR · Punjab · Haryana · UP)₹410 Cr
55%
11% / 12%Watch
Egypt 500 kV OHTL (EETC)EETC (Egypt) / InternationalInternational EPC (MENA & Africa)International (MENA · Africa)₹400 Cr
15%
10% / 13%Watch
Raipur–Tiroda 400 kV D/C line (217 km)Adani Energy SolutionsPower Transmission (Lines & Substations ≤765 kV)East (West Bengal · Bihar · Odisha)₹300 Cr
60%
10% / 12%On track
Data-centre 400/220/33 kV GIS substationData-centre & new-segmentPower Transmission (Lines & Substations ≤765 kV)West (Maharashtra · Gujarat · MP)₹300 Cr
20%
12% / 15%On track
Pune 765 kV AIS substation + Karjat / Lonikand baysState utilities (MPPTCL·KPTCL·MSETCL·HVPNL…)Power Transmission (Lines & Substations ≤765 kV)West (Maharashtra · Gujarat · MP)₹250 Cr
30%
12% / 14%On track
Bellary–Davanagere 400 kV RE-evacuationKPTCL & other STUsPower Distribution (Rural/Urban & Schemes)South (Karnataka · AP · Telangana · TN)₹220 Cr
25%
9% / 12%Watch
Ranjangaon galvanizing expansion (40,500→110,000 MT)Internal (Capex)Monopoles, Structures & Galvanizing (Ranjangaon)West (Maharashtra · Gujarat · MP)₹170 Cr
40%
0% / 0%On track
Mandsaur 765/400/220 kV substation bay extensionPower Grid Corp (PGCIL)Power Transmission (Lines & Substations ≤765 kV)North (Delhi-NCR · Punjab · Haryana · UP)₹150 Cr
65%
11% / 12%On track
Where margin is slipping

8 projects below target · ₹53 Cr at stake

The fastest margin recovery is on projects already in execution — tighten scope, subcontract & commodity cost before they commission.

Egypt 500 kV OHTL (EETC)
EETC (Egypt) / International · International EPC (MENA & Africa) · International (MENA · Africa) · 15% complete
Margin gap
3pt
At stake
₹12 Cr
Data-centre 400/220/33 kV GIS substation
Data-centre & new-segment · Power Transmission (Lines & Substations ≤765 kV) · West (Maharashtra · Gujarat · MP) · 20% complete
Margin gap
3pt
At stake
₹9 Cr
Kurnool-IV → Kurnool-III 765 kV D/C line
Power Grid Corp (PGCIL) · Power Transmission (Lines & Substations ≤765 kV) · South (Karnataka · AP · Telangana · TN) · 45% complete
Margin gap
2pt
At stake
₹8 Cr
Bellary–Davanagere 400 kV RE-evacuation
KPTCL & other STUs · Power Distribution (Rural/Urban & Schemes) · South (Karnataka · AP · Telangana · TN) · 25% complete
Margin gap
3pt
At stake
₹7 Cr
Raipur–Tiroda 400 kV D/C line (217 km)
Adani Energy Solutions · Power Transmission (Lines & Substations ≤765 kV) · East (West Bengal · Bihar · Odisha) · 60% complete
Margin gap
2pt
At stake
₹6 Cr
Pune 765 kV AIS substation + Karjat / Lonikand bays
State utilities (MPPTCL·KPTCL·MSETCL·HVPNL…) · Power Transmission (Lines & Substations ≤765 kV) · West (Maharashtra · Gujarat · MP) · 30% complete
Margin gap
2pt
At stake
₹5 Cr
Vindhyachal Pool–Prayagraj 765 kV D/C (87.3 km)
Power Grid Corp (PGCIL) · Power Transmission (Lines & Substations ≤765 kV) · North (Delhi-NCR · Punjab · Haryana · UP) · 55% complete
Margin gap
1pt
At stake
₹4 Cr
Mandsaur 765/400/220 kV substation bay extension
Power Grid Corp (PGCIL) · Power Transmission (Lines & Substations ≤765 kV) · North (Delhi-NCR · Punjab · Haryana · UP) · 65% complete
Margin gap
1pt
At stake
₹2 Cr

Act now: the Egypt 500 kV OHTL (EETC) project is 15% executed at 10% vs a 13% target — recover via scope, subcontract & commodity-cost discipline before it commissions, because once the project commissions the margin is locked in.